north logo transparent

Industrial Complex for Aluminum Can Production

Investor : BALL PAKOVANJA EVROPA BEOGRAD d.o.o.

Location

Zemun, Belgrade

Design year

Phase 1 –2004-2005
Phase 2 –2018-2019
Phase 3 –2021-2022

Year of performance

Phase 1–2005
Phase 2 – 2019-2020
Phase 3 – 2023

Area

42.490 m2

The industrial complex for the production of aluminum beverage cans “Ball Packaging Europe Belgrade” was built in 2004/05 in the industrial zone of the Municipality of Zemun.
At that time, a production and warehouse hall with two production lines was constructed, along with an administrative building and several auxiliary facilities, including a scrap aluminum warehouse, pallet storage, a gatehouse, a transformer station, and fire water reservoirs.
During 2018 and 2019, the investor expanded the capacity of the complex through the reconstruction, conversion, adaptation, and extension of the existing facilities: the production and warehouse hall and the administrative building. These works were carried out in order to increase production capacity and to introduce production line 3.
Phase 3 of the expansion refers to the installation of production line 4 within the production and warehouse facility.